Mamlaka ya Viwanja vya Ndege Tanzania

"Inaunganisha Tanzania na Dunia"
ISO Imethibitishwa 9001:2015; 14001:2015 & 45001:2018

Maendeleo Ya Viwanja Vya Ndege

Maeneo
Rehabilitation and Upgrading of Shinyanga Airport

Scope of Work (Major Items):

  • Runway (2,000m longx30m)
  • Passenger Terminal Building (1,400m2)
  • Aircraft apron (10,400m2)
  •  taxiway
  • Car Parking
  • Access road
  • Storm water drainage
  • Substation
  • Perimeter security fencing
  • Other general utilities/ services works

Expected Achievements /Outcomes:

  • Improved runway, apron and taxiways condition and performance;
  • Provide safe and smooth aircraft operations activities; and
  • Reduced aircraft operation and maintenance cost.

 

 

Taarifa za urekebishaji

Bei : 52,867,897,637.00 Tsh

Hali : OnProgress

Mfadhili : European Investment Bank (EIB)

Mahali : Shinyanga Airport

Muda : Eighteen (18) months