Refurbishment and face lifting of JNIA TB I - Improvement of Pavement at Car Parking

  1. Asphalt Patching (100m3)
  2. Asphalt concrete (2000m2) 
  3. Construction of insitu kerbstones (80m3) 
  4. Drainage works (new catch water drop 3No and raising existing manhole 19No)
  5. Laying of Paving blocks (950m2)
  6. Thermoplastic paint (350m2)
  7. Landscaping (43 Trees)

Details


  • Price: TZS 1,030,924,548.00
  • Financier: OwnSource
  • Duration: 6 Months
  • Status: Completed
  • Location: Julius Nyerere International Airport