TAA Project Profile


Project Name: Construction of new songwe airport
Donor/Financier:BADEA/OPEC/Goverment
Contract No.:TAA/C/19/2008/2009
Project costs:TShs 34 billion (Contractor & Consultant)
Date of signing Contract:12th September 2008
Contract duration:18 months from commencement date
Contractor:M/s Kundan Singh Construction Limited – KENYA
Supervision Consultant:M/s United Engineering and Technical Consultants (UNETEC) – DUBAI
Date of site handing over to Contractor10th October 2008
Mobilisation period:10th October 2008 – 9th February 2009
Commencement date:10th February 2009
Scope of works
  1. Construction of base course and surfacing (tarmac) on the runway, taxiway, apron, access road and car parking.
  2. Construction of storm water drainage system
  3. Construction of Terminal Building
  4. Construction of Meteorological Observatory Building
  5. Completion of the existing airport buildings (Fire station, Air traffic control tower, Administration building, etc)
  6. Installation of various equipment and systems in the airport buildings
Budgeted amount (in millions)

Donor: TShs 9,000.00

Govt: TShs 11,000.00

Amount spent (in millions)

Donor: Nil

Govt: TShs 6,317.00

Performance progress status
  1. Construction of runway and taxiway completed to bitumen standard.
  2. Construction of base course on apron is completed and the Contractor is in preparations for construction of surfacing (rigid pavement).
  3. Construction of access road and car parking to bitumen standard is completed.
  4. Construction of storm water drainage systems in progress.
  5. Construction of Terminal Building is in progress, the Contractor is due to cast concrete on the first floor slab.
  6. Roofing works for construction of Meterological Obersevatory Building is completed. Finishing works are in progress.
  7. Construction of Waste water Stabilisation Ponds completed.
  8. Drilling of 3 deep bore holes with a total capacity of 15000 liters per hour is completed.

Challenges

  1. Delay of Advance Payments to Contractor.
  2. Substantial increase of earth works (about 7 times).
  3. Change of design of base course from Crushed stone base course to Cement stabilized base course.
  4. Antagonism between the Contractor and Consultant.
  5. Only portion of Government funds released. Some of the amount paid is from TAA revenues.
  6. Donor funds (BADEA) have not been paid from IPC No. 6 to IPC No.12


Project Name: Rehabilitation and upgrading of the airport
Donor/Financier:UNCHR/Goverment
Contract No.:AE-027/2009-10/HQ/W/33
Project costs:Tanzania Shillings 30 billion (Contractor & Consultant)
Date of signing Contract:28th January 2010
Contract duration:12 months from commencent date
Contractor:M/s db shapriya + co ltd – TANZANIA
Supervision Consultant:M/s Crown-TECH Consult –TANZANIA
Date of site handing over to Contractor15th February 2010
Mobilisation period:15th February 2010 – 14th April 2010
Commencement date:15th April 2010
Scope of works
  1. Rehabilitation and construction of runway, taxiways, access roads and car parking to asphalt standards
  2. Construction of runway strips and grassing
  3. Construction of storm water drainage system
  4. Construction of security fence, etc
Budgeted amount (in millions)

Donor: NIL

Govt: TShs 9,000.00

Amount spent (in millions)

Donor: NIL

Govt:  TShs 5,887.00

Performance progress status

The project works have been completed.

Some additional works (water reserve tank and terminal buiding renovation works are under finalisation of design by the Consultant)


Challenges

  1. Interference among railway, road and airport infrastructures.
  2. Only portion of Government funds released. Some of the amount paid is from TAA revenues.


Project Name: Rehabilitation and upgrading of Kigoma airport
Donor/Financier:World Bank/Government
Contract No.:AE-027/2011-2012/KGM/W/06
Works Contract Price:Tanzania Shillings 20,491,117,159.80
Consultancy Contract Price:Tanzania Shillings 4,622,100,000.00
Date of signing Contract:15th September 2011
Contract duration:18 months from commencement date
Contractor:Sinohydro Corporation Limited – CHINA
Supervision Consultant:M/s SSI Engineers and Environmental Consultants [Pty] – SOUTH AFRICA in association with Howard Humphreys – TANZANIA, etc
Date of site handing over to Contractor18th October 2011
Commencement date:14th December 2011
Completion date:13th June 2013
Scope of works
  1. Rehabilitation and upgrading of runway to asphalt standards.
  2. Construction of runway strips and grassing
  3. Construction of storm water drainage system
Budgeted amount (in millions)

Donor: TShs 13,820.00

Govt:   TShs 1,500.00

Amount spent (in millions)

Donor: TShs 2,515.00

Govt:   TShs 518.00

(Advance Payment)

Performance progress status

The Contractor is in progress with mobilisation (equipment, staff, site camp, site offices and materials)

Challenge

Funds have not yet been released from Treasury. Government portion (17%) paid from TAA revenues. This has disturbed other project plans under TAA financing.


Project Name: Rehabilitation and upgrading of Bukoba airport
Donor/Financier:World Bank/Goverment
Contract No.:AE-027/2011-2012/BKB/W/05
Contract Price:Tanzania Shillings 21,014,671,848.98
Date of signing Contract:15th September 2011
Contract duration:18 months from commencement
Contractor:M/s MECCO – TANZANIA in JV with CGG Spa – ITALIA
Supervision Consultant:M/s SSI Engineers and Environmental Consultants [Pty] – SOUTH AFRICA in association with Howard Humphreys – TANZANIA, etc
Date of site handing over to Contractor22nd October 2011
Mobilisation period:22nd October 2011 – 21st January 2012
Commencement date:14th February 2012
Completion date:13th August 2013
Scope of works
  1. Rehabilitation of runway to asphalt standards
  2. Construction of taxiway and apron to asphalt standards
  3. Construction of runway & taxiway strips and grassing
  4. Construction of storm water drainage system
  5. Construction of access road and car parking to asphalt standards
  6. Construction of new Terminal Building
  7. Construction of Power House/Station
  8. Construction of Security/Perimeter Fence
Budgeted amount (in millions)

Donor: TShs 11,083.00

Govt:   TShs 1,000.00

Amount spent (in millions)

Donor: TShs 2,611.00

Govt:   TShs 541.00

(Advance Payment)

Performance progress status

The Contractor is in progress with mobilisation (equipment, staff, site camp, site offices and materials)


Challenge

Funds have not yet been released from Treasury. Government portion (17%) paid from TAA revenues. This has disturbed other project plans under TAA financing.


Project Name: Rehabilitation and upgrading of Tabora airport
Donor/Financier:World Bank/Goverment
Contract No.:AE-027/2011-2012/TBR/W/07
Work Contract Price:Tanzania Shillings 11,652,591,923.70
Date of signing Contract:15th September 2011
Contract duration:15 months from commencement date
Contractor:Sinohydro Corporation Limited - CHINA
Supervision Consultant:M/s SSI Engineers and Environmental Consultants [Pty] – SOUTH AFRICA in association with Howard Humphreys – TANZANIA, etc
Date of site handing over to Contractor20th October 2011
Commencement date:14th December 2011
Completion date:13th March 2013
Scope of works
  1. Rehabilitation and upgrading of runway to asphalt standards.
  2. Construction of runway strips and grassing
  3. Construction of storm water drainage system
Budgeted amount (in millions)

Donor: TShs 11,083.00 

Govt:   TShs 1,000.00

Amount spent (in millions)

Donor: TShs 1,432.00

Govt:   TShs 293.00

(Advance Payment)

Performance progress status

The Contractor is in progress with mobilisation (equipment, staff, site camp, site offices and materials)

 

Challenge

Funds have not yet been released from Treasury. Government portion (17%) paid from TAA revenues. This has disturbed other project plans under TAA financing.