Flight Information Display System (FIDS) Under-construction ........

Project Name: Completion of construction of three buildings
Donor/Financier:Government
Contract No.:AE-027/2011 – 12/W/SGW/16
Project Cost:TShs 3,509,289,419.77 (works) and TShs 221 million (supervision)
Contractor:M/s Beijing Engineering Construction Group Co. Ltd - CHINA
Supervision Consultant:M/s Crown TECH Consult Ltd - TANZANIA
Date of site handing over to Contractor3rd March 2012
Mobilisation period:4th March 2012 – 10th March 2012
Commencement date:11th March 2012
Original Completion date:1st May 2012
Revised completion date:1st August, 2012
Scope of worksCompletion of finishing works of Control Tower, Old Terminal building and Fire Station
Budgeted amount (in millions)

Nil


Amount spent (in millions)

TShs 546.00

(Advance Payment)

Performance progress status

The Contractor is in progress with mobilisation (equipment, staff, site camp, site offices and materials)

Challenge

No funds received from Treasury leading to the delay of advance payments (paid on 2nd May 2012) hence delay of commencement of the project. This will as well delay commencement of operations of the airport