Flight Information Display System (FIDS) Under-construction ........

JNIA Project Profile

  • CONSTRUCTION OF TAXIWAY TO PRECISION AIR HANGAR

    Financier: TAA
    Contract No.: AE-027/2010-11/HQ/W/16
    Project cost: Tanzania Shillings 717,884,167.30
    Date of Contract signing: 11th May 2011
    Contract duration: 3 months from commencement date
    Contractor: M/s CATIC International Engineering (T) Ltd –TANZANIA
    Supervisor: Engineering & Technical Services Department –TAA 
    Date of site handing over to the Contractor: May 2011
    Commencement date: 20th May 2011 
    Completion date: 21st August 2011 
    Revised completion date: 31st January 2012
    Scope Of Works:
    1. Construction of taxiway to aircraft hangar for Precision Air to asphalt standards.
    2. Construction of storm water drainage system.
    Budgeted Amount (In Millions): Nil
    Amount Spent (In Millions): TShs 435,439,820.52
    Performance Progress Status: Works are in progress; the Contractor has completed priming works ready to commence construction of asphalt layer.

    SUPPLY AND INSTALLATION OF DAIKIN VRV TYPE AIR CONDITIONING

    Financier: TAA
    Contract No.: AE-027/209/2010/HQ/W/43
    Project cost: Tanzania Shillings 647,454,202.36
    Date of Contract signing: 8th June 2010
    Contract duration: 7 months from commencement
    Contractor: M/s DAIKIN TANZANIA LIMITED –TANZANIA
    Supervisor: Engineering & Technical Services Department –TAA 
    Supervisor Engineering & Technical Services Department –TAA 
    Commencement date: July 2010
    Completion date: August 2011 
    Revised completion date: 31st January 2012
    Scope Of Works:

    The installation involved 18 Units:

    1. 7 units in Check-in-Hall
    2. 11 units in Arrival Hall  
    Budgeted Amount (In Millions): Funds used were budgeted in 2010/2011
    Amount Spent (In Millions): TShs 221,753,046.00 
    Performance Progress Status: Works completed
  • Compensation of Kipunguni Residents and Surveying of Alternative Plots

    Completion of Construction of Three Buildings at Songwe Airport

    Compensations to Vunja Nazi Residents at Mafia Airprot

    Construction of Triple Culverts & Gabion Protection

    Rehabilitation and Uprading of Arusha Airport

    Construction of the New Msalato Airport

    Rehabilitation and Uprading of Singida Airport

  • Nil